Article Details

Stakeholder Management is a Front-End Risk Elimination

image

Stakeholder Management is a Front-End Risk Elimination

author

By Fabio Gaignoux

January 09, 2026

In mining and metals projects, most risks are not technical. Instead, they are alignment risks discovered too late.

Yet, in many organisations I have worked for, they still treat stakeholder management as a soft activity — something to be handled alongside engineering, rather than before it. Evidence from major mining projects shows the opposite: early stakeholder engagement and aligment is one of the strongest predictors of cost, schedule, and value certainty.

The PMI Textbook vs Reality

According to the Project Management Institute (PMI), stakeholder management is a structured discipline:

  • Identify stakeholders
  • Analyse influence and interest
  • Plan engagement
  • Manage and monitor alignment

In theory, this should prevent late surprises. In practice, alignment is often delayed — and replaced by a simple spreadsheet and engineering effort that looks like progress but avoids hard decisions.

What Mining Project Data Actually Shows

Empirical benchmarking by Independent Project Analysis (IPA) consistently shows:

⚠️ Decisions made before ~15% of project spend lock in ~80% of lifecycle cost

⚠️ Misalignment discovered after FEL 2 drives:

  • Late scope changes
  • Rework
  • CAPEX escalation
  • Schedule blowouts

Stakeholder issues rarely disappear — they simply resurface as “engineering changes”.

Communities and Environmental Stakeholders Are Schedule-Critical

In mining projects, social licence, Traditional Owners, and environmental regulators are often treated as external constraints rather than core design inputs.

When these stakeholders are engaged late, risks materialise as:

  • Approval delays
  • Redesign and scope change
  • Legal challenge
  • Reputational damage

High-performing projects integrate community and environmental requirements early, treating them as front-end risk elimination, not downstream compliance.

Operations Is Not a Reviewer — It Is a Co-Owner of Design

One of the most common failure points in mining projects is late Operations involvement. When Operations is treated as a reviewer or commissioning stakeholder, the outcome is predictable:

  • No Operation Readiness planning
  • Maintainability issues
  • OPEX locked in too high
  • Changes during construction or ramp-up

The best projects I've worked on, treat Operations as a co-owner of the design from FEL 1. But it is rare rather than normal practice.

Why Owners team Still Over-Focus on Engineering

Because engineering:

  • Feels objective and controllable
  • Is easy to contract and govern
  • Looks good in board packs

Stakeholder alignment, by contrast:

  • Forces early trade-offs
  • Requires senior accountability
  • Locks decisions before all answers are known

So organisations default to what feels safe — even when it isn’t.

IPA describes this pattern bluntly:

Engineering is often used as a substitute for decision-making.

The Way Forward: Strong Steering Committees

Successful mining and metals projects don’t reduce engineering effort — they move alignment upstream.

Effective steering committees: ✔️ Own stakeholder alignment ✔️ Resolve value vs cost vs risk trade-offs early (VIP)s) ✔️ Prevent re-litigation of settled decisions ✔️ Focus on decisions, not presentations

Final Thought

Engineering locks value in. Stakeholder alignment decides whether that value exists.

The best mining projects I've worked on, don’t start with better flowsheets or layouts — they start with early engagement, better decisions made earlier, by the right people. Because Stakeholder Management is an efective way of Front-End Risk Elimination!